Olsson Industrial Electric completed a project to replace several existing Woodward governors at the Bonneville Lock and Dam, Powerhouse II. Olsson removed the existing mechanical governors and associated controls. New conduit and cabling was installed to support the replacement digital governors in main units 11-18 and fish units F1 and F2. In addition, Olsson repaired and refurbished several distributing valves, designed and fabricated transducer mounting brackets and performed asbestos abatement.