Seneca Sawmill Co-Gen Facility

Overview

Olsson Industrial Electric and Olsson Controls were hired to complete the electrical installation of Seneca Sawmill’s Co-Generation facility located in Eugene, OR.

Scope

  • Installation of 15kV plant-wide distribution
  • 480VAC MCC installation in the following locations: Truck Dump Area, Fuel Handling and Storage System, and Co-Gen building
  • PLC/Control System installation in the following locations: Truck Dump Area, Fuel Handling and Storage System, and Co-Gen building
  • Documentation and rewiring of controls on 19MW generator
  • Installation of a plant-wide lighting system

Highlights

  • Zero safety incidents
Client: Seneca Sawmill Company
Location: Eugene, Oregon
Timeline: 2010
Divisions: Construction & Controls
Value: $2,600,000

Related Projects

Superior Energy Arctic Challenger

Read more
Superior Energy Arctic Challenger
electricians

Kapstone #11 Paper Machine HCR Refiner and ENP Press Project

Read more
Kapstone #11 Paper Machine HCR Refiner and ENP Press Project
Electrical installation

Schnitzer Steel Mega Shredder – Electrical Installation

Read more
Schnitzer Steel Mega Shredder – Electrical Installation

Back to Projects