Olsson Industrial Electric served as the lead electrical and controls contractor for a >$100M capital improvement project, increasing production capacity by more than 40,000 tons of containerboard per year. The Olsson construction management team worked hand-in-hand with the customer to plan and execute a complex construction sequence, maximizing pre-outage construction opportunities, streamlining the outage construction schedule, and minimizing overtime costs. Installation, testing and commissioning was handled by a robust team of experienced Olsson electricians and controls technicians. Featuring more than 60 on-site during critical outages, the Olsson team completed this project with craftsman quality and zero safety incidents.
International Paper – Paper Machine Productivity Improvements
Overview
Highlights
- No lost time, injuries or accidents
- All work completed on or ahead of time and under budget
- Over 60 personnel worked safely 24/7 during a 5-week shutdown
Client: International Paper Company | |
Location: Springfield, Oregon | |
Timeline: 2015-2017 | |
Divisions: Construction, Controls & Engineering | |
Value: > $6,250,000 |
Category:
Heavy Industrial Electrical Construction | |
Plant Automation | |
Automation System Analysis |
Industry Served:
Pulp & Paper |
Area Served:
Oregon |
Download a PDF of this page
Related Projects
Vera Water & Power 16th Avenue Substation
Read moreVera Water & Power 16th Avenue Substation
The John Day North Fish Ladder AWS Pump Replacement
Read moreThe John Day North Fish Ladder AWS Pump Replacement
The Dalles Dam Station Service Improvements
Read moreThe Dalles Dam Station Service Improvements