In 2007, Olsson Industrial Electric completed an electrical installation at Schnitzer Steel’s brand new facility in Portland, Oregon.
Schnitzer Steel Mega Shredder – Electrical Installation
Overview
Scope
Olsson installed the following items:
- 12.5 kV power distribution
- 4160 V power distribution
- 3,400 concrete encased duct bank
- Substation building electrical
- Shredder Building electrical and controls
- Water system power, controls and instrumentation
- Fiber-optic communication system
- Camera system
Highlights
- Zero safety incidents
Client: Schnitzer Steel | |
Location: Portland, Oregon | |
Timeline: 2007 | |
Divisions: Construction, Controls & Engineering | |
Value: $2,950,000 |
Category:
Hydro Design | |
Power System Design & Analysis | |
Automation System Analysis |
Industry Served:
Metal & Recycling |
Area Served:
Washington |