Olsson Industrial Electric completed a project in the spring of 2012 that included the start-up and commissioning of a paper mill that had been shuttered for the past five years. Due to a compressed construction schedule, the Olsson field crew worked around the clock in order to complete the project. The project featured 24-hour staffing.
Greenberry Cosmo Specialty Fibers Paper Mill Start-Up
Overview
Scope
- Replaced 2,478 total instruments
- Inspected conduit and fittings, and repaired any issues found
- Instruments were tested for functionality and to verify information to PLC or DCS
- Damaged instruments and wires were repaired or replaced
- 250 process critical instruments were bench calibrated, the remaining 2,228 were field calibrated
- Performed point check for all I/O points and DCS loops
- Made PLC, HMI, and DCS programming changes as needed for the new owner’s process
- Repaired or replaced PLC, HMI, and DCS as needed
- Replaced 1,163 total motors
- MCC buckets were inspected and cleaned, and repaired any issues found
- Meggered all motors, and replaced or repaired any issues found
- Bumped each motor to verify rotation
- Medium Voltage Switch Gear was inspected, cleaned and tested
- Transformers and breakers were tested, and all issues were repaired or replaced
Highlights
- Zero safety incidents
Client: Greenberry Industrial | |
Location: Cosmopolis, Washington | |
Timeline: 2012 | |
Divisions: Construction, Controls & Engineering | |
Value: $4,000,000 |
Category:
Hydro Design | |
Power System Design & Analysis | |
Automation System Analysis |
Industry Served:
Pulp & Paper |
Area Served:
Washington |
Download a PDF of this page
Related Projects

The John Day North Fish Ladder AWS Pump Replacement
Read moreThe John Day North Fish Ladder AWS Pump Replacement