Olsson Industrial Electric completed a project in the spring of 2012 that included the start-up and commissioning of a paper mill that had been shuttered for the past five years. Due to a compressed construction schedule, the Olsson field crew worked around the clock in order to complete the project. The project featured 24-hour staffing.
Greenberry Cosmo Specialty Fibers Paper Mill Start-Up
Overview
Scope
- Replaced 2,478 total instruments
- Inspected conduit and fittings, and repaired any issues found
- Instruments were tested for functionality and to verify information to PLC or DCS
- Damaged instruments and wires were repaired or replaced
- 250 process critical instruments were bench calibrated, the remaining 2,228 were field calibrated
- Performed point check for all I/O points and DCS loops
- Made PLC, HMI, and DCS programming changes as needed for the new owner’s process
- Repaired or replaced PLC, HMI, and DCS as needed
- Replaced 1,163 total motors
- MCC buckets were inspected and cleaned, and repaired any issues found
- Meggered all motors, and replaced or repaired any issues found
- Bumped each motor to verify rotation
- Medium Voltage Switch Gear was inspected, cleaned and tested
- Transformers and breakers were tested, and all issues were repaired or replaced
Highlights
- Zero safety incidents
Client: Greenberry Industrial | |
Location: Cosmopolis, Washington | |
Timeline: 2012 | |
Divisions: Construction, Controls & Engineering | |
Value: $4,000,000 |
Category:
Hydro Design | |
Power System Design & Analysis | |
Automation System Analysis |
Industry Served:
Pulp & Paper |
Area Served:
Washington |
Download a PDF of this page
Related Projects
Vera Water & Power 16th Avenue Substation
Read moreVera Water & Power 16th Avenue Substation
The John Day North Fish Ladder AWS Pump Replacement
Read moreThe John Day North Fish Ladder AWS Pump Replacement
The Dalles Dam Station Service Improvements
Read moreThe Dalles Dam Station Service Improvements