While working with Vera Water and Power, OS Engineering determined that additional system capacity was needed to meet growth requirements to provide quality reliability in the near and long-term future. OS Engineering prepared complete design drawings for the construction of Vera’s 16th Avenue Substation as well as provided services during construction including relay settings and start-up assistance.

Scope

  • Prepared and distributed Power Transformer Contract Documents followed by evaluation and award recommendation (service included witnessing transformer testing)
  • Prepared and distributed Circuit Switcher Contract Documents followed by evaluation and award recommendation
  • Prepared and distributed Relay and Control Panel Contract Documents followed by evaluation and award recommendation
  • Prepared complete project design drawings
  • Prepared and distributed Substation Construction Contract Documents, including pre-bid meeting presentation followed by evaluation and award recommendation
  • Provided services during construction to respond to and resolve any issues that arose during construction
  • Provided relay settings, programming and start-up assistance

Highlights

  • The substation was energized in October 2016 and has been reliable to Vera customers since
Client: Vera Water & Power
Location: Spokane Valley, Washington
Timeline: February 2015 – October 2016
Division: Engineering
Value: $2,400,000

Category:

Heavy Industrial Electrical Construction
Power Distribution
Power System Design & Analysis
Automation System Analysis

Industry Served:

Utilities

Area Served:

Washington
Download a PDF of this page

Related Projects

Substation

Vera Water & Power 16th Avenue Substation

Read more
Vera Water & Power 16th Avenue Substation

The John Day North Fish Ladder AWS Pump Replacement

Read more
The John Day North Fish Ladder AWS Pump Replacement

Back to Projects