Olsson Industrial Electric completed a project in the Spring of 2012 that included a complete start-up and commissioning of a paper mill that was previously shutdown for 5 years. Due to a short schedule, labor was provided 24 hours a day, 7 days a week.

Scope

  • Replaced 2,478 total instruments.
  • Inspected conduit and fittings, and repaired any issues found.
  • Instruments were tested for functionality and to verify information to PLC or DCS.
  • Damaged instruments and wire were repaired or replaced.
  • 250 process critical instruments were bench calibrated, the remaining 2,228 were field calibrated.
  • Performed point check for all I/O points and DCS loops.
  • Made PLC, HMI, and DCS programming changes as needed for the new owner’s process.
  • Repaired or replaced PLC, HMI, and DCS as needed.
  • Replaced 1,163 total motors.
  • MCC buckets were inspected and cleaned, and repaired any issues found.
  • Meggered all motors, and replaced or repaired any issues found.
  • Bumped each motor to verify rotation.
  • Medium Voltage Switch Gear was inspected, cleaned and tested. Transformers and breakers were tested and all issues were repaired or replaced.

Highlights

  • Zero safety incidents
Client: Greenberry Industrial
Location: Cosmopolis, Washington
Completed: 2012
Divisions: Construction, Controls & Engineering
Value: $4,000,000

Related Projects

Superior Energy Arctic Challenger

Read more
Superior Energy Arctic Challenger
electricians

Kapstone #11 Paper Machine HCR Refiner and ENP Press Project

Read more
Kapstone #11 Paper Machine HCR Refiner and ENP Press Project
Electrical installation

Schnitzer Steel Mega Shredder – Electrical Installation

Read more
Schnitzer Steel Mega Shredder – Electrical Installation

Back to Projects