Full Service Projects

Kapstone #11 Paper Machine HCR Refiner and ENP Press Project

Overview In 2013, Olsson Industrial Electric completed a project for Kapstone involving a commissioning shutdown that required 48 electricians on a 24-hour schedule for 4 days. Scope13.8 kV power distribution13.8 kV soft start575 V switchgear12,000 HP motor and control installationBasler …

Schnitzer Steel Mega Shredder – Electrical Installation

Overview In 2007, Olsson Industrial Electric completed an electrical installation at Schnitzer Steel's brand new facility in Portland, Oregon. Scope Olsson installed the following items: 12.5 kV power distribution4160 V power distribution3,400 concrete encased duct bankSubstation building electricalShredder Building electrical …

Greenberry Cosmo Specialty Fibers Paper Mill Start-Up

Overview Olsson Industrial Electric completed a project in the spring of 2012 that included the start-up and commissioning of a paper mill that had been shuttered for the past five years. Due to a compressed construction schedule, the Olsson field crew …

Bonneville Lock and Dam Digital Governor Installation

Overview Olsson Industrial Electric completed a project to replace several existing Woodward governors at the Bonneville Lock and Dam, Powerhouse II. Olsson removed the existing mechanical governors and associated controls. New conduit and cabling was installed to support the replacement …

Seneca Sawmill Capital Upgrade

Overview Olsson Industrial Electric was selected to expand and upgrade the power distribution system at the Seneca Sawmill facility located in Eugene, OR – a $3M project. Designed and built by Olsson, the power distribution expansion includes: the relocation and …